Skip to main content

MAP of Forest-Watershed Road Work Status 

See Roads Work Status as of November 2024.

 

The roads repair and decommissioning work has concluded for this year-1 work period.  The second and final work period will be from May – September 2025.  The below map shows the roads repair work that has been completed (green circles), the roads that have been decommissioned (red dashed lines) and the roads that have been abandoned (pink dashed lines).  The map also shows the work for next year -  roads repair work (red circles) and the roads to be decommissioned (red solid lines).   Mark Morgans, our forester, and Vinson Brothers, our roads contractor, have completed a lot of work and are on pace for an on-time and in-budget finish.

A map showing maintained roads in Arch Cape Forest with symbols indicating road maintenance status, stream sizes, and property boundaries.